Reykjavík ordered to re-tender Borgarlína traffic lights and pay ISK 1m
A complaints committee annulled the city's purchase of traffic-light equipment for two Snorrabraut junctions, saying it should have been advertised across the EEA.
Reykjavík must re-tender a traffic-light contract for two Snorrabraut junctions across the European Economic Area (EEA) after a complaints committee annulled the procurement, mbl.is reported on Sunday.
The Public Procurement Complaints Committee (Kærunefnd útboðsmála) also ordered the city to pay ISK 1 million (about €7,300 / $8,000) in legal costs to Reykjafell, the company that brought the complaint. The ruling is dated 9 November and was published on Friday.
The contract covers the supply and installation of traffic-light equipment where Snorrabraut meets Hverfisgata and where it meets Laugavegur, in central Reykjavík. The work is part of the first phase of Borgarlína, the planned rapid bus system for the capital region.
The city sent a price inquiry to selected companies on 3 July. Reykjafell was one of them and lodged its complaint on 23 July. The committee suspended the process on 21 September while it considered the case.
Reykjavík argued that the purchase fell under special procurement rules for transport services, which carry a higher threshold for EEA-wide tendering. The committee rejected this, saying the equipment was meant to control traffic at junctions in the city’s general street network.
In deciding whether the contract had to be tendered, the committee took into account that the city regularly replaces traffic-light equipment at junctions. The city’s contracts for such equipment totalled ISK 59.1 million, excluding VAT, in the 12 months before the price inquiry was sent. The threshold for municipal goods contracts was ISK 31.9 million.
Given the scale of similar purchases over that period, the committee found that the city should have advertised the contract in the EEA.
Reykjafell’s other arguments were rejected. The company said a requirement that the equipment connect to the city’s central traffic-light control computer had been tailored to products from Yunex Traffic. The committee said the case documents did not support this and pointed to undisputed information from the city that Reykjafell equipment had previously been connected to the computer without problems.
Because no bids were received, the committee did not consider that Reykjafell had incurred costs in preparing a bid and taking part in the process. It declined to give an opinion on whether the city was liable for damages.
The committee also turned down Reykjafell’s demand that the city’s contracts for buying and upgrading the central control system be declared ineffective, because the deadline for complaining about those contracts had passed.
As mbl.is first reported.